Synthetic track progress at Corbould Park
The first synthetic racing and training surface in Queensland is well on the way towards completion. The following pictures show the development progress.
The proposed finished aerial view of Corbould Park (3MB)
UPDATE: Monday, November 19
Drainage layer fabric prior to the laying of the 40mm gravel

Commencement of the drainage layer to a depth of 150mm using 40mm gravel
 
Herring bone drainage pipes running into the Vee drain

Stock pile of the Cushion Track

Cushion Track material

Maintenance equipment – Power Harrow

40mm drainage aggregate laid over the western end of the synthetic track.
.JPG)
Herring bone drainage trench.
.JPG)
Service road located inside the synthetic track.
.JPG)
Newly shaped Vee drain on the inside of the synthetic track.
.JPG)
The mixing mill.
.jpg)
The outside kerb on the synthetic track.
.jpg)
Laying of the kerb on the synthetic track.
.jpg)
.
|